PJM 5400 Module 2 Written Assignment: Choosing Contract Types for Meters, Installation and Integration Example

Reviewed by Edgar Pennington, MBA Thomas Edison State University Updated October 2026

This PJM 5400 Module 2 example answers a written assignment on contracting principles and methods in Procurement and Vendor Management, part of TESU's Master of Science in Management in Project Management. PJM-5400 asks in this module what makes a contract valid, which law governs it and how the choice of contract type allocates risk between buyer and seller. The paper applies these principles to the smart meter program of the composite Monmouth County utility introduced in Module 1. It sets out the elements of a valid contract, distinguishes goods from services under the law, and chooses a different contract type for each of the program's three purchases, explaining how each allocates cost risk.

CoursePJM-5400 Procurement and Vendor Management
ModuleModule 2
Paper typeModule 2 written assignment: contracting principles and methods
LengthAbout 555 words, 5 pages
FormatAPA 7 student paper
SchoolThomas Edison State University
ProgramM.S. in Management in Project Management
UpdatedOctober 2026

Free sample paper for PJM 5400 Module 2

1

Three Purchases, Three Contract Types: Matching Risk to Pricing in a Smart Meter Program

Student Name

M.S. in Management in Project Management, Thomas Edison State University

PJM-5400: Procurement and Vendor Management

Mentor Name

Month Day, Year

What this page is doingThe title states the paper's main decision, that each part of the program calls for a different contract type.
2

Three Purchases, Three Contract Types: Matching Risk to Pricing in a Smart Meter Program

Elements of a Valid Contract

Garrett (2010) lists the elements of a binding contract: an offer, acceptance of that offer, consideration exchanged between the parties, parties with legal capacity to contract and a lawful purpose. For a public utility, authority also matters: only officials authorized by the board can bind the utility, so the RFP will name the contracting officer and state that no other employee may commit the utility.

Goods and Services

The program combines goods and services. Sales of goods, such as meters and radio equipment, fall under Article 2 of the Uniform Commercial Code, whose default rules fill gaps, on warranties and delivery for example, wherever the contract says nothing. Installation and billing integration are services, governed by common law. Separating the purchases, or stating clearly which rules apply to each part, avoids disputes about which law controls. Public buyers must also justify contract choices to boards and the public, a constraint Schapper et al. (2006) place at the center of public procurement management.

Contract Types and Risk

Garrett describes a spectrum of contract types. At one end, firm-fixed-price contracts place cost risk on the seller; at the other, cost-reimbursement contracts place it on the buyer. Time-and-materials contracts pay for hours and materials as used. Bajari and Tadelis (2001) showed that fixed-price contracts give strong incentives to control cost but become costly to change, while cost-plus contracts adapt easily but weaken incentives, so the right choice depends on how complete and stable the design is.

PurchaseUncertaintyContract typeReason
Meters and network equipmentLow in design; moderate in component pricesFixed price with economic price adjustmentSpecifications are standard, but electronic component prices have swung sharply; an adjustment tied to a published index shares that risk fairly
Installation of 48,000 metersModerate: access, basement conditions, customer schedulingFixed unit price per meter, with an incentive for on-time completionUnit pricing handles volume; the incentive rewards meeting the schedule
Billing system integrationHigh: our billing system is old and poorly documentedTime and materials with a not-to-exceed ceilingScope cannot be defined precisely; the ceiling protects the utility
What this page is doingMatching each contract type to the uncertainty in each purchase, rather than choosing one type for the whole program, applies the principle that contract type should follow risk.
3

Why Not One Contract Type

A single firm-fixed-price contract for everything would push all risk onto the vendor, which would price in large contingencies for the billing integration and installation surprises, raising the total cost. A single cost-reimbursement contract would leave the utility exposed on meters, where prices can be fixed. Matching type to risk lets each risk sit where it can best be managed.

Protections in Each Type

The economic price adjustment will be limited to plus or minus 10 percent and tied to a published producer price index for electronic components. The installation contract will define what counts as a difficult access case, such as a meter behind a finished wall, with a separate unit price, so the installer is not forced to absorb unforeseen work. The integration ceiling will be set at $650,000, with work authorized in monthly task orders.

Conclusion

A valid contract needs offer, acceptance, consideration, capacity and a lawful purpose, plus authority on the utility's side. Choosing a different contract type for meters, installation and integration places each risk with the party best able to manage it, which should lower bids and reduce disputes.

References

Bajari, P., & Tadelis, S. (2001). Incentives versus transaction costs: A theory of procurement contracts. RAND Journal of Economics, 32(3), 387-407. https://doi.org/10.2307/2696361

Garrett, G. A. (2010). World class contracting (5th ed.). CCH.

Schapper, P. R., Veiga Malta, J. N., & Gilbert, D. L. (2006). An analytical framework for the management and reform of public procurement. Journal of Public Procurement, 6(1/2), 1-26. https://doi.org/10.1108/JOPP-06-01-02-2006-B001

PJM 5400 Module 2 instructions, in plain terms

This written assignment covers contracting principles and methods, and Part 1 of the course project, the Instructions to Bidders section of an RFP, is due at the end of this module. You will set out what makes a contract valid, which law governs goods and which services, and the spectrum of contract types, then pick a type for each part of a purchase and defend it by its risks. Show how each type shifts cost risk between buyer and seller, and add protections that make the choice work. Treat each part of a mixed procurement separately if its risks differ, and explain which law governs goods and which governs services. Use a table to set each purchase beside its contract type.

How the PJM 5400 Module 2 example is put together

The paper lists the elements of a valid contract and adds the question of authority for a public buyer. A section distinguishes goods under the Uniform Commercial Code from services. A section explains the spectrum of contract types with research on incentives and flexibility, and a table assigns a type to each of three purchases with reasons. Sections explain why one type would not fit and the protections built into each. Protections are spelled out for each contract type: limits on price adjustment, a defined difficult-access category and a not-to-exceed ceiling for integration work. A section explains why a single contract type for the whole program would raise cost or exposure. Each contract type is tied to the uncertainty in its purchase.

PJM 5400 Module 2 rubric: what earns full marks

The grade reflects accurate explanation of contract principles, sound reasoning about contract types and risk, and specific application. Papers that match contract type to the uncertainty of each purchase show command of the module. Distinguishing goods from services, and noting authority to contract, demonstrates legal awareness. Protections such as indexes, defined exceptions and ceilings show practical skill. Specific protections, tied to each contract type, show that the choice has been thought through to the clauses that make it work. Explaining why one type would not fit the whole program shows the reasoning behind the choice. Noting who may legally bind the utility shows awareness of public authority.

Common PJM 5400 Module 2 mistakes, and how to avoid them

Students lose points by choosing one contract type without considering risk, by confusing time and materials with cost-plus or by ignoring the law that governs goods. Others list contract elements without applying them. Match contract type to uncertainty. Explain who bears cost risk under each. Add protections. Note which law governs each purchase. Write the protections that make each contract type safe, such as indexes, defined exceptions and ceilings. Remember that the right type for one purchase can be wrong for another in the same program. A free first sample on your own PJM-5400 contracting assignment is available on request.

Write yours, or have the desk draft it

This paper is an original model document written by our desk, not a submitted student paper and not an official Thomas Edison State University document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.

More PJM 5400 and M.S. in Management in Project Management sample papers

PJM 5400 Module 2 questions, answered

Where can I find a free PJM 5400 Module 2 sample paper?

Contract types chosen for meters, installation and integration in a smart meter program are in the assignment above.

What are the elements of a valid contract?

An offer and its acceptance, an exchange of value, parties able to contract and a legal purpose.

What law governs the sale of goods?

Article 2 of the Uniform Commercial Code, while services fall under common law.

When is a fixed-price contract appropriate?

When requirements are well defined and stable, so the seller can price the risk.

What is an economic price adjustment?

A clause that adjusts a fixed price for changes in a published index, sharing the risk of market price swings.