PJM 6400 Module 3 Case Analysis: A Global Matrix and the Two-Boss Problem Example

Reviewed by Edgar Pennington, MBA Thomas Edison State University Updated October 2026

This PJM 6400 Module 3 sample answers a case analysis on global organizations in Global Project Management, from TESU's Master of Science in Management in Project Management, discussed in the course's synchronous session. PJM-6400 asks in this module how global organizations structure themselves for projects, and why matrix structures, though common, are hard to run. The firm analyzed is the same composite New Brunswick device designer, whose engineers report to site managers in four countries while working on programs led by program managers in New Jersey. Conflicts over priorities have delayed two programs. It compares structures, recommends a balanced matrix with clear decision rights and adds practices that build the frame of mind a matrix needs.

CoursePJM-6400 Global Project Management
ModuleModule 3
Paper typeModule 3 case analysis: global organizations
LengthAbout 465 words, 4 pages
FormatAPA 7 student paper
SchoolThomas Edison State University
ProgramM.S. in Management in Project Management
UpdatedOctober 2026

Free sample paper for PJM 6400 Module 3

1

Two Bosses, Four Countries: Making a Global Matrix Work for Device Programs

Student Name

M.S. in Management in Project Management, Thomas Edison State University

PJM-6400: Global Project Management

Mentor Name

Month Day, Year

What this page is doingThe title names the central difficulty of matrix structures, dual reporting, magnified by distance.
2

Two Bosses, Four Countries: Making a Global Matrix Work for Device Programs

The Situation

Each site manager controls engineers' hiring, pay and daily assignments. Program managers in New Brunswick are accountable to clients for schedule and budget but control no one. When the Galway site manager moved two verification engineers to a higher-margin client, the infusion pump program lost three weeks. Engineers say they do not know whose priorities come first.

Structural Options

Galbraith (1971) described a range of structures between a functional organization, organized by discipline, and a project organization, organized by product or program, with matrix forms in between that give authority to both functional and project managers in varying balance.

Kerzner (2014) observes that companies moving toward project management excellence often adopt matrix structures, and that the matrix works when authority, responsibility and accountability are clearly divided and when senior management resolves conflicts quickly.

StructureStrengthsWeaknesses for this firm
Functional (by site)Deep expertise, career paths, efficient use of specialistsPrograms have no authority; priorities set locally
Project (by program)Clear authority, client focusDuplicates specialists across programs; weak technical development
Weak matrixSites keep control; programs coordinateCurrent situation: programs cannot hold resources
Balanced matrixShared authority; clear decision rightsRequires agreement on who decides what
Strong matrixProgram managers control resourcesUndermines site expertise and careers

Recommendation: A Balanced Matrix With Clear Decision Rights

The key rule: once a site manager commits an engineer to a program for a phase, the engineer cannot be moved without the program manager's agreement or a decision by the resource council.

DecisionProgram managerSite manager
What work is done and whenDecidesConsulted
Who does the workRequests named peopleDecides, honoring commitments
How technical work is doneConsultedDecides
Reassignment of a committed engineerMust agreeProposes
Performance reviewContributes written inputDecides
What this page is doingWriting decision rights into a table, especially the rule on reassignment, addresses the specific conflict that delayed the programs rather than restructuring in general terms.
3

A Frame of Mind, Not Only a Structure

Bartlett and Ghoshal (1990) argued that matrix management fails when firms rely on structure alone and that success depends on building a matrix in managers' minds: a shared vision, developed people and a culture of cooperation across lines. Three practices support this. A quarterly resource council of site and program managers will plan capacity across programs. Site managers will carry shared goals for on-time program delivery, not only site margin. And engineers will receive a one-page assignment statement each phase naming their program and priorities.

Risks

Site managers may resist losing control of reassignments; involving them in designing the decision rights, and giving them a seat on the council, reduces that risk.

Conclusion

A balanced matrix with written decision rights, a resource council and shared goals gives programs the stability they need while preserving site expertise, and it treats the matrix as a way of working rather than a chart.

References

Bartlett, C. A., & Ghoshal, S. (1990). Matrix management: Not a structure, a frame of mind. Harvard Business Review, 68(4), 138-145.

Galbraith, J. R. (1971). Matrix organization designs: How to combine functional and project forms. Business Horizons, 14(1), 29-40. https://doi.org/10.1016/0007-6813(71)90037-1

Kerzner, H. (2014). Project management best practices: Achieving global excellence (3rd ed.). Wiley.

Reading the PJM 6400 Module 3 assignment instructions

The Module 3 case analysis is discussed in the course's synchronous session, worth 10 percent of the grade. Expect to analyze how a global organization structures itself for projects, compare structural options, recommend one and explain how to make it work in practice. Use a table to compare structures and another to divide decision rights, and draw on the textbook and research on matrix management. Prepare to discuss your analysis with classmates during the live session. Describe a specific conflict the current structure has caused, and show how your recommendation would have prevented it. Consider how those who lose authority will respond. Bring specific questions about your recommendation to the live session, since classmates will test it. Show both sides' authority in one table.

How the PJM 6400 Module 3 example is put together

The analysis describes a conflict between site and program managers and its cost. A table compares five structures with their strengths and weaknesses for this firm, drawing on research and the textbook. A decision rights table recommends a balanced matrix and highlights the reassignment rule. A section on the matrix as a frame of mind proposes three practices, and risks and a conclusion follow. Three practices, a resource council, shared goals for site managers and assignment statements for engineers, turn the matrix structure into a working arrangement. A short risks section addresses site managers' likely resistance and how involving them reduces it. Engineers receive one-page assignment statements.

PJM 6400 Module 3 rubric: what earns full marks

Mentors grade this case analysis on accurate comparison of structures, a well-justified recommendation, practical measures to make it work and readiness to discuss it in the live session. Analyses that specify decision rights, rather than naming a structure, show practical insight. Recognizing that a matrix depends on mindset as well as structure demonstrates depth. Addressing likely resistance shows realism. Practices that build cooperation across reporting lines show that the analysis understands matrix management as behavior as well as structure. Tying the reassignment rule to the conflict that caused delays shows focus. Clear tables for structures and decision rights make the recommendation easy to evaluate and discuss.

PJM 6400 Module 3 help: mistakes that cost marks

Students lose points by recommending a structure without explaining how authority is divided, by ignoring the people who lose authority or by treating structure as the whole answer. Others compare structures in general terms. Compare options for your organization specifically. Divide decision rights in writing. Add practices that build cooperation. Plan for resistance. Show how your structure would have prevented the conflict that started the case, and plan for those who lose authority. Write the rule that would have prevented the conflict, and test it against a likely future dispute. A free first sample on your own PJM-6400 global organizations case is available on request.

Write yours, or have the desk draft it

This paper is an original model document written by our desk, not a submitted student paper and not an official Thomas Edison State University document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.

More PJM 6400 and M.S. in Management in Project Management sample papers

PJM 6400 Module 3 questions, answered

Where can I find a free PJM 6400 Module 3 sample paper?

The analysis above recommends a balanced matrix for a four-country device firm.

What is a matrix organization?

A structure in which people report to both a functional manager and a project or program manager.

What is the difference between a weak and a strong matrix?

In a weak matrix functional managers hold most authority; in a strong matrix project managers do.

Why do matrix structures fail?

Often because authority is unclear and firms rely on structure without building cooperation and shared goals.

What are decision rights?

A written division of which manager decides, is consulted or must agree on each type of decision.