PJM 5400 Module 3 Written Assignment: The RFP, Evaluation Criteria and a Best Value Source Selection Plan Example

Reviewed by Edgar Pennington, MBA Thomas Edison State University Updated October 2026

This PJM 5400 Module 3 sample answers a written assignment on the pre-award contract phase in Procurement and Vendor Management, from TESU's Master of Science in Management in Project Management. PJM-5400 asks in this module how buyers prepare to solicit offers: structuring the request for proposal, setting evaluation criteria and planning source selection. The paper prepares the pre-award phase for the composite utility's meter replacement in Monmouth County. It outlines the RFP, chooses a best value tradeoff approach over lowest price technically acceptable, sets weighted evaluation criteria, and describes the evaluation committee, scoring rubric and safeguards that make the selection defensible.

CoursePJM-5400 Procurement and Vendor Management
ModuleModule 3
Paper typeModule 3 written assignment: the pre-award contract phase
LengthAbout 565 words, 5 pages
FormatAPA 7 student paper
SchoolThomas Edison State University
ProgramM.S. in Management in Project Management
UpdatedOctober 2026

Free sample paper for PJM 5400 Module 3

1

Best Value, Not Lowest Price: Building the Evaluation Before Anyone Bids

Student Name

M.S. in Management in Project Management, Thomas Edison State University

PJM-5400: Procurement and Vendor Management

Mentor Name

Month Day, Year

What this page is doingThe title states the evaluation approach the paper chooses and stresses that criteria are set before proposals arrive.
2

Best Value, Not Lowest Price: Building the Evaluation Before Anyone Bids

Structuring the RFP

Garrett (2010) emphasizes that a well-structured solicitation tells sellers exactly what is wanted, how to respond and how they will be judged. Federal practice organizes solicitations in a uniform contract format, with instructions to offerors and evaluation factors in separate sections; our RFP follows a similar logic.

SectionContents
Instructions to biddersDeadlines, format, questions process, pre-proposal conference
Scope of workMeters and network, installation, billing integration, with performance standards
Pricing scheduleUnit prices, adjustment index, integration rates and ceiling
Terms and conditionsInsurance, bonds, warranties, data ownership, termination
Evaluation criteriaFactors, weights and method
Required formsAffidavits required under state public contracting law

Best Value or Lowest Price

Federal regulations describe a best value continuum: when requirements are clear and risk is low, lowest price technically acceptable may be appropriate; when non-price factors matter, a tradeoff process allows award to other than the lowest-priced offer (Federal Acquisition Regulation, 2024). Our program involves 48,000 customers' homes, a radio network that must cover hilly terrain and a vendor relationship of three years or more. Non-price factors matter, so we will use a best value tradeoff.

Evaluation Criteria

Schapper et al. (2006) describe public procurement as balancing competing goals: value for money, transparency, fairness and broader policy aims. The weights express our balance: price matters, but not so much that a vendor with a poor installation record could win on price alone.

FactorWeightWhat evaluators look for
Technical approach35 percentMeter accuracy, network coverage study for our terrain, data security
Past performance25 percentSimilar programs of 25,000 or more meters, on time and on budget; references
Price30 percentTotal evaluated price over three years, including adjustment scenarios
Customer service plan10 percentAppointment scheduling, installer conduct, complaint handling
What this page is doingExplaining the weights as a statement of the utility's priorities makes the evaluation defensible to bidders and the public, which is the purpose of setting them in advance.
3

The Source Selection Plan

Separating technical and price evaluation prevents a low price from coloring technical judgments.

ElementPlan
Evaluation committeeEngineering lead, operations supervisor, finance analyst and customer service manager; procurement manager facilitates without scoring
Scoring guideFive-point scale for each factor with written definitions of each score
Price evaluationFinance analyst evaluates price separately; committee scores technical factors without seeing price first
Conflicts of interestEvery evaluator signs a disclosure; anyone with ties to a bidder is replaced
DocumentationEach evaluator writes reasons for each score; the committee records its consensus
Competitive range and negotiationsThe utility may hold discussions with the highest-rated offerors before final offers

Pre-proposal Conference and Questions

A pre-proposal conference three weeks after the RFP is issued will walk bidders through the scope and take questions; a site tour will show typical basement installations and the hilly areas where coverage is hardest. All questions must be submitted in writing by a stated date, and answers will be issued to every bidder as a numbered addendum. Bidders must acknowledge each addendum in their proposals, so no one can claim they missed a change.

Schedule

The RFP will be open for six weeks, evaluation will take four weeks and negotiations two, so the board can approve an award about three months after release.

Conclusion

A structured RFP, a best value tradeoff justified by the program's risks, published weights and a source selection plan with clear scoring and safeguards make the award defensible and give bidders confidence that the best proposal, not the best connected bidder, will win.

References

Federal Acquisition Regulation, 48 C.F.R. pt. 15 (2024).

Garrett, G. A. (2010). World class contracting (5th ed.). CCH.

Schapper, P. R., Veiga Malta, J. N., & Gilbert, D. L. (2006). An analytical framework for the management and reform of public procurement. Journal of Public Procurement, 6(1/2), 1-26. https://doi.org/10.1108/JOPP-06-01-02-2006-B001

PJM 5400 Module 3 instructions, in plain terms

This written assignment covers the pre-award contract phase. Expect to outline a solicitation, choose an evaluation approach, set criteria and weights and plan how proposals will be evaluated fairly. Use tables for the RFP structure, criteria and source selection plan, and justify the approach and weights by the procurement's risks and priorities. This work also supports Part 2 of the course project, the remaining sections of your RFP, due at the end of Module 4. Set evaluation weights before any proposals arrive, and explain them as the buyer's priorities. Plan how questions from bidders will be answered fairly and on what schedule. Name who will score and who will facilitate.

How the PJM 5400 Module 3 example is put together

The paper outlines six RFP sections in a table. A section chooses a best value tradeoff over lowest price technically acceptable, citing federal regulations. A table sets four weighted factors and what evaluators look for, and the text explains the weights as priorities with research on public procurement goals. A table sets out the source selection plan, including separate price evaluation and conflict rules, and the conclusion ties the pieces to a defensible award. Sections on the pre-proposal conference, written questions answered by numbered addendum and a three-month schedule complete the pre-award plan. A source selection table names evaluators, scoring rules, conflict safeguards and documentation. The weights are explained as the utility's priorities, so price matters without letting a poor installer win on price alone. The RFP outline uses six sections with their contents.

Reading the PJM 5400 Module 3 grading rubric

Mentors grade this assignment on a sound solicitation structure, a justified evaluation approach, criteria and weights tied to priorities, and a fair, documented source selection plan. Papers that justify best value or lowest price by the procurement's risks show understanding. Separating technical and price evaluation, and managing conflicts of interest, demonstrate command of fair process. Clear scoring definitions show the plan can be applied consistently. A fair questions process, with answers shared through addenda, shows command of transparent solicitation practice. A realistic schedule shows planning. Separating price from technical scoring shows care for fairness. Written score definitions let evaluators score consistently.

PJM 5400 Module 3 help: mistakes that cost marks

Students lose points by choosing an evaluation approach without justification, by setting weights without explaining them or by leaving out conflict of interest and documentation rules. Others let evaluators see price before technical scoring. Justify your approach. Explain your weights. Define scores in writing. Plan for conflicts and documentation. Share every answer with every bidder, and require acknowledgment of each addendum. Publish the weights in the RFP so bidders know how they will be judged, and keep price scoring separate from technical scoring. A free first sample on your own PJM-5400 pre-award assignment is available on request.

Write yours, or have the desk draft it

This paper is an original model document written by our desk, not a submitted student paper and not an official Thomas Edison State University document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.

More PJM 5400 and M.S. in Management in Project Management sample papers

PJM 5400 Module 3 questions, answered

Where can I find a free PJM 5400 Module 3 sample paper?

The assignment above outlines an RFP, weighted criteria and a source selection plan for a utility's meter program.

What is a best value tradeoff?

An evaluation approach that allows award to other than the lowest-priced offer when non-price factors justify it.

When is lowest price technically acceptable appropriate?

When requirements are clear and performance risk is low, so price can decide among acceptable offers.

Why evaluate price separately from technical factors?

To keep a low price from influencing judgments of technical quality.

What does a source selection plan include?

The evaluation committee, scoring rubric, price evaluation method, conflict rules and documentation requirements.