Free sample paper for PJM 7210 Module 4
From Charter to Closeout: An Integrated Plan for a Four-Year Lead Line Program, With the First Phase's Earned Value at Week Eight
Student Name
Master of Business Administration, Thomas Edison State University
PJM-7210: Project Management
Mentor Name
Month Day, Year
From Charter to Closeout: An Integrated Plan for a Four-Year Lead Line Program, With the First Phase's Earned Value at Week Eight
Project Charter
This final project, prepared by a four-person team, plans the lead service line replacement program of Ramapo Valley Water Authority, a composite water utility serving part of Bergen County, New Jersey. The program's purpose is to remove every known lead service line from the system, about 1,200 lines, by replacing each in full from the water main to the customer's meter within four years and a budget of $14.4 million, financed largely through the state's revolving fund for drinking water. The sponsor is the authority's executive director; the project manager is the engineering division's deputy director; and the steering committee includes finance, customer service and the borough engineers of the two towns served. Success will be measured by lines replaced, post-replacement water tests below the federal action level, schedule and budget performance, and customer satisfaction with notification and restoration.
Scope and Work Breakdown Structure
The deliverable-based WBS has five branches: 1.0 service line inventory and verification; 2.0 customer engagement, consent and communication; 3.0 construction, divided into eight neighborhood phases of about 150 lines each; 4.0 restoration and testing; and 5.0 project management. Each neighborhood phase is a control account with its own crew assignments, budget and schedule. Exclusions are stated in the charter: household plumbing inside the home and replacement of water mains are out of scope, apart from any main excavated to get at a service line. Larson and Gray (2018) emphasize that a clear scope and WBS are the basis for every later plan, and the control accounts here make later earned value reporting possible.
Schedule, Resources and Budget
Each neighborhood phase follows the six-activity network developed in Module 3: mobilization, public-side and private-side replacement, street and lawn restoration, and testing. With three in-house crews, each phase takes about 17 weeks, and phases overlap so that a new phase mobilizes as the previous one moves into restoration, giving roughly two phases a year plus winter work on inventory and outreach. The schedule avoids starting phases after mid-September to keep paving out of the winter shutdown.
The budget allocates about $1.8 million to each of the eight phases, with additional amounts for inventory, outreach and project management held within the $14.4 million total, and a contingency reserve held by the steering committee rather than spread across phases. Because federal funds flow through the state revolving fund, iron and steel products and construction materials must meet Buy America requirements, so the procurement plan verifies domestic sourcing for pipe, fittings and meter boxes before contracts are awarded.
Risk Management
The risk register carries the risks identified in the midterm, with owners and triggers: homeowner refusal of access, surprises in the ground, for instance service lines running beneath a foundation, contractor and paving capacity, cost inflation, and supply delays for compliant materials. The highest-rated risk is homeowner refusal, since partial replacement would leave lead in place and can temporarily raise lead levels (Trueman et al., 2016); the response is intensive outreach, door-to-door scheduling and help with consent forms, with refusals escalated to customer service after three attempts.
Monitoring: Earned Value Eight Weeks Into Phase 1
Larson and Gray (2018) recommend earned value as the integrated measure of schedule and cost performance, and Anbari (2003) shows how its indexes support forecasts that managers can act on. At the end of week 8 of the first phase, with a budget at completion of $1.8 million, the planned value was $820,000, the earned value of completed work was $760,000 and actual costs were $805,000.
| Measure | Value |
|---|---|
| Planned value (PV) | $820,000 |
| Earned value (EV) | $760,000 |
| Actual cost (AC) | $805,000 |
| Schedule variance (EV minus PV) | minus $60,000 |
| Cost variance (EV minus AC) | minus $45,000 |
| Schedule performance index (EV / PV) | 0.93 |
| CPI, earned value divided by actual cost | 0.94 |
| Forecast final cost, budget divided by CPI | about $1,907,000 |
| To-complete performance index ((BAC minus EV) / (BAC minus AC)) | 1.05 |
The phase was 7 percent behind schedule and 6 percent over cost. At the current schedule performance, the 17-week phase would take about 18.3 weeks. The team traced most of the variance to private-side work: lines under driveways required more saw cutting and restoration than estimated, and eleven homeowners delayed access. To finish within the original budget, the remaining work must be done 5 percent more efficiently than budgeted, which is unrealistic, so the team recommended releasing about $107,000 from contingency, the gap between the estimate at completion and the phase budget, adjusting the private-side estimate for later phases using the actual driveway rate, and adding a Saturday crew for three weeks to recover the schedule before paving season ends.
Procurement and Contract Control
Most field work is delivered by contractors, so contract terms are part of the control system. Line replacement is bought under unit-price contracts, which pay a set amount for each completed and inspected service line, so payment tracks earned value directly. The authority withholds 5 percent retainage on each invoice until restoration in the phase is accepted, which keeps contractors attentive to the final, least glamorous work. Change orders above $25,000 require steering committee approval, and smaller ones are logged against the phase contingency. Materials are checked at delivery for the domestic sourcing documentation the federal loan requires, since a missing certificate can delay reimbursement for an entire phase. The program manager reviews contractor performance each quarter on schedule, quality and community complaints, and the results inform awards for later phases.
Teams and Communication
The textbook's chapter on teams stresses shared goals, clear roles and routines that keep a team aligned. The program team meets weekly, publishes a two-page status report to the steering committee every two weeks with earned value, risks and decisions needed, and holds a monthly public update with the boroughs. Field crews receive a one-page phase plan with the week's addresses, and customer service receives the same plan so that calls are answered with current information.
Closure Plan
Each phase closes formally, and the program closes after the last phase. Closure includes verifying that every line in the phase is recorded as replaced in the inventory, that water tests are complete and filed, that restoration punch lists are cleared and that contractor accounts are settled. Larson and Gray (2018) recommend a post-project review to capture lessons; the program will hold a short review after each phase, so that lessons such as the driveway rate improve the next phase rather than only the final report.
Conclusion
The integrated plan connects a clear charter and deliverable-based WBS to a phased schedule, budgets by control account, a risk register and a monitoring system based on earned value. The first phase's week-8 report shows the plan working as intended: modest variances were detected early, traced to causes and corrected with specific actions, and the lessons were fed into estimates for later phases.
References
Anbari, F. T. (2003). Earned value project management method and extensions. Project Management Journal, 34(4), 12-23. https://doi.org/10.1177/875697280303400403
Larson, E. W., & Gray, C. F. (2018). Project management: The managerial process (7th ed.). McGraw-Hill Education.
Trueman, B. F., Camara, E., & Gagnon, G. A. (2016). Evaluating the effects of full and partial lead service line replacement on lead levels in drinking water. Environmental Science & Technology, 50(14), 7389-7396. https://doi.org/10.1021/acs.est.6b01912
Reading the PJM 7210 Module 4 assignment instructions
The PJM-7210 final project is a group project based on the textbook's project appendix and covers most of the course's topics, such as developing a project plan, scheduling, resources and budgets, and monitoring progress. Module 4 adds project teams, monitoring with earned value, international projects and closure. Agree on roles within your group early, use one consistent project throughout, and include a status report or monitoring plan, since control is the part of planning students most often leave out. Keep the plan's numbers consistent from section to section, since schedule, budget and status figures are checked against one another, and make sure your status report uses a realistic point partway through the work.
Inside the PJM 7210 Module 4 example
The plan follows the life of a project in order: charter, scope and WBS, schedule and resources, budget, risk, monitoring, teams and closure. Each section builds on earlier course assignments rather than repeating them. A table presents earned value at a realistic status point, and the interpretation traces variances to causes, tests whether recovery is realistic with the to-complete index and states corrective actions. A closure plan with phase-level reviews shows how lessons improve later work. Earlier course work, such as the selection exercises, midterm scope and Module 3 schedule, is carried forward and refined rather than rewritten, which shows how a real plan matures over time. Each section feeds the control system.
Reading the PJM 7210 Module 4 grading rubric
The final project is scored out of 100 and is the culminating work of PJM-7210. Mentors look for a complete, internally consistent plan, correct application of scheduling, budgeting and earned value methods, risks matched with credible responses, and attention to team communication and closure. Showing how monitoring leads to corrective action demonstrates mastery. Clear tables, APA citations and a professional presentation suitable for a sponsor complete a strong submission. Mentors also reward realism: plans that respect resource limits, seasonal constraints and regulatory requirements, and status reports whose corrective actions are specific, earn the highest marks. A professional format a sponsor could read quickly is part of the assessment. Consistent figures across sections also earn credit. Accuracy in the indexes matters.
Common PJM 7210 Module 4 mistakes, and how to avoid them
Group plans often stitch together sections written by different members that do not agree, for example a schedule that ignores the resource limits in another section. Assign one member to check consistency. Include a monitoring section with earned value or a similar measure and explain what you would do about variances. Our writers can prepare a PJM 7210 final project plan for the project your group has chosen. Do not stop at the plan; show how it will be controlled. Report variances with their causes, decide whether recovery is realistic and name the actions you would take. Include a closure plan with lessons learned, which many groups forget until the last day.
Write yours, or have the desk draft it
This paper is an original model document written by our desk, not a submitted student paper and not an official Thomas Edison State University document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.
More PJM 7210 and Master of Business Administration sample papers
- PJM 7210 Module 1: Project Selection Exercises
- PJM 7210 Module 2: Midterm Essay Assignment
- PJM 7210 Module 3: Resources and Crashing Exercises
- HRM 7600 Module 4: Midterm: Four HR Situations
- ENP 7320 Module 3: Business Plan Part 3: The Financial and Financing Plans
- GSM 7300 Module 6: Final Paper: Strategic Entrepreneurship
- NEG 7310 Module 6: Discussion: What to Say About a Used Rooftop Unit's Leak History
PJM 7210 Module 4 questions, answered
Where can I find a free PJM 7210 Module 4 sample paper?
The Project Management final project is shown above: an integrated plan for a lead line replacement program, with an earned value status report at week 8 of the first phase and a closure plan.
What does the to-complete performance index show?
The efficiency the remaining work must achieve to finish within budget; a value well above 1.0 suggests the budget is unlikely to be met without changes.
What is a control account?
A part of the work breakdown structure where scope, budget and schedule are integrated and performance is measured, often with earned value.
Is the PJM-7210 final project done individually?
No; it is a group project based on the textbook's project appendix.
Why hold reviews after each phase rather than only at the end?
Phase reviews capture lessons while they can still improve estimates and methods for the remaining phases.