Ten Risks in Cause, Event and Effect: Identifying What Could Derail a Packaging Line
Student Name
M.S. in Management in Project Management, Thomas Edison State University
PJM-5300: Project Risk Management
Mentor Name
Month Day, Year
Ten Risks in Cause, Event and Effect: Identifying What Could Derail a Packaging Line
Identification Techniques
Kendrick (2015) stresses that risk identification starts with thorough planning: the work breakdown structure and schedule reveal risks in each activity and dependency. He also draws on the PERIL database, a collection of problems reported by project managers, which shows that scope, schedule and resource risks dominate real projects. I used four techniques.
| Technique | What it found |
|---|---|
| Work breakdown review | Integration of the line with our serialization system has no owner |
| Team brainstorm with engineering, quality, validation and maintenance | Compressed air capacity may be insufficient; operators need certification |
| Review against PERIL categories and our past projects | Vendor delays and late scope changes were common on our last two lines |
| Assumption analysis | We assumed the client's blister format is final; the client has not signed off |
Stating Risks Precisely
Hillson (2002) recommended stating each risk in three parts, sometimes called a risk metalanguage: a cause, the uncertain event it could trigger and the effect that event would have. This format separates the risk from its cause and its consequence, so responses can target the right one.
The Risk Register
| ID | Because of (cause) | This may occur (event) | Leading to (effect) | Owner | P | I | Score |
|---|---|---|---|---|---|---|---|
| R1 | Vendor's order backlog | Line ships 4 or more weeks late | Validation and client start slip | Project manager | 3 | 4 | 12 |
| R2 | New vision inspection camera model | Camera fails validation tests | Rework and revalidation; 2 to 4 weeks | Validation lead | 2 | 4 | 8 |
| R3 | Client's format not signed off | Blister dimensions change after design | Tooling rework, $90,000 | Account manager | 2 | 4 | 8 |
| R4 | Line uses more air than current system | Compressed air capacity insufficient | Utility upgrade, $35,000 and 2 weeks | Facilities manager | 2 | 3 | 6 |
| R5 | One validation engineer knows our protocols | Engineer leaves during the project | Validation delays | Quality director | 1 | 4 | 4 |
| R6 | Serialization integration has no owner | Integration not ready at installation | Line cannot run commercially | IT manager | 3 | 4 | 12 |
| R7 | New thermoforming technology | Operators not certified in time | Start delayed | Training lead | 2 | 3 | 6 |
| R8 | Cleanroom shutdown needed | Shutdown overlaps another client's campaign | Lost revenue or delay | Operations director | 2 | 3 | 6 |
| R9 | Exchange rate on euro-priced line | Euro strengthens before final payment | Cost rises up to $60,000 | Finance | 3 | 3 | 9 |
| R10 | Vendor finishes early (opportunity) | Line arrives 2 weeks early | Earlier operator training | Project manager | 2 | 2 | 4 |
Priorities
Two risks score 12, above the plan's threshold for reporting to the sponsor: late vendor shipment and the unowned serialization integration. R6 is unusual: its cause is a gap in our own plan, so it can be removed by assigning an owner and adding integration tasks to the schedule. Raz et al. (2002) found that risk management practices were associated with better project outcomes, especially in projects with high technological uncertainty, which describes the vision system and the new thermoforming technology here.
Next Steps
Owners will draft responses for R1, R6 and R9 by the next biweekly review, and the validation lead will quantify R2 in the activity risk analysis of Module 3.
Conclusion
Four techniques found ten risks, including one that was really a planning gap. Stating each as cause, event and effect, with an owner and a score, makes the register a tool for action rather than a list of worries.
References
Hillson, D. (2002). Extending the risk process to manage opportunities. International Journal of Project Management, 20(3), 235-240. https://doi.org/10.1016/S0263-7863(01)00074-6
Kendrick, T. (2015). Identifying and managing project risk: Essential tools for failure-proofing your project (3rd ed.). AMACOM.
Raz, T., Shenhar, A. J., & Dvir, D. (2002). Risk management, project success, and technological uncertainty. R&D Management, 32(2), 101-109. https://doi.org/10.1111/1467-9310.00243
Reading the PJM 5300 Module 2 assignment instructions
PJM-5300 includes four case studies, together worth 30 percent of the grade, two of them accompanied by live sessions in Modules 3 and 5. This case covers risk identification. Expect to apply several identification techniques to a project, state risks precisely, record them in a register with causes, effects, owners and scores, and decide which need responses first. Use the scales from your risk management plan so the scores mean something, and look for risks that are really gaps in the plan. Include at least one opportunity in the register, and check your assumptions as a source of risk, since unchecked assumptions often hide the largest exposures. Use the scoring scales from your risk plan.
How the PJM 5300 Module 2 example is put together
The case applies four identification techniques in a table, noting what each found, and draws on the PERIL database. A section introduces the cause, event and effect format with research support. A register lists ten risks, including an opportunity, with owners and scores. A priorities section explains which risks exceed the threshold and why one is a planning gap, with research on technological uncertainty. Next steps and a conclusion follow. The register includes an opportunity, early delivery, and an assumption that turned out to be a risk, the unsigned blister format, showing that identification covers more than obvious threats. Each technique is credited with what it found, so the reader can see why several were used. The priorities section explains why two risks exceed the reporting threshold.
Where the marks sit in the PJM 5300 Module 2 rubric
Mentors grade case studies on correct use of identification techniques, precise risk statements, a complete register and sound priorities. Papers that write risks in cause, event and effect form show precision. Using several techniques, and showing what each found, demonstrates thoroughness. Recognizing that some risks are planning gaps to close now shows practical judgment beyond filling in a template. Including opportunities and assumption risks shows command of the full identification process. Next steps with dates and owners show that the register will drive action. A register with owners and scores for every risk is ready to manage.
Common PJM 5300 Module 2 mistakes, and how to avoid them
Students lose points by listing vague risks such as "schedule delays," by confusing causes with risks or by leaving owners blank. Others identify risks from intuition alone. Use more than one technique. Write each risk as cause, event and effect. Assign an owner and score each risk with your plan's scales. Look for gaps you can close immediately. Check every assumption in your plan, and add at least one opportunity to the register. Name an owner for every risk before the first review, and rate each with the same scales. A free first sample on your own PJM-5300 risk identification case is available on request.
Write yours, or have the desk draft it
This paper is an original model document written by our desk, not a submitted student paper and not an official Thomas Edison State University document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.
More PJM 5300 and M.S. in Management in Project Management sample papers
- PJM 5300 Module 1: Written Assignment: A Risk Management Plan for a Blister Packaging Line
- PJM 5300 Module 3: Case Study: Three-Point Estimates and the Chance of Meeting the Start Date
- PJM 5300 Module 4: Written Assignment: Expected Monetary Value, a Decision Tree and the Contingency Reserve
- PJM 5300 Module 5: Case Study: Risk Reviews, a Trigger Fired and Closing the Register
- PJM 5400 Module 2: Written Assignment: Choosing Contract Types for Meters, Installation and Integration
- PJM 6400 Module 5: Final Project: A Report to Executives on a Global Project Management Office
- PJM 5200 Module 3: Written Assignment: Monitoring, a Slipping Milestone and a Clean Closure
PJM 5300 Module 2 questions, answered
Where can I find a free PJM 5300 Module 2 sample paper?
A ten-risk register for a packaging line installation is the case study above.
What is the cause, event and effect format?
A three-part risk statement naming a cause, the uncertain event it could set off and the effect that would follow.
What is the PERIL database?
Kendrick's collection of problems reported by project managers, used to find common sources of project risk.
What techniques identify project risks?
Work breakdown and schedule review, brainstorming, lessons from past projects and assumption analysis, among others.
How many case studies does PJM-5300 require?
Four case studies, which carry 30 percent of the course grade.