PJM 5300 Module 1 Written Assignment: A Risk Management Plan for a Blister Packaging Line Example

Reviewed by Edgar Pennington, MBA Thomas Edison State University Updated October 2026

This PJM 5300 Module 1 sample answers a written assignment on risk planning in Project Risk Management, a course in TESU's Master of Science in Management in Project Management. PJM-5300 opens with planning how risk will be managed before identifying any risk: who is responsible, how risks will be rated, when they must be escalated and how reserves will be set. Its author manages projects for a composite contract packaging company in Somerset, New Jersey, and is installing a $2.4 million blister packaging line for a pharmaceutical client within nine months. It presents a risk management plan with roles, categories, rating scales, thresholds, reserves and a review cycle, and explains why each choice fits a regulated project.

CoursePJM-5300 Project Risk Management
ModuleModule 1
Paper typeModule 1 written assignment: risk planning
LengthAbout 621 words, 5 pages
FormatAPA 7 student paper
SchoolThomas Edison State University
ProgramM.S. in Management in Project Management
UpdatedOctober 2026

Free sample paper for PJM 5300 Module 1

1

Deciding How to Decide: A Risk Management Plan for a Packaging Line Installation

Student Name

M.S. in Management in Project Management, Thomas Edison State University

PJM-5300: Project Risk Management

Mentor Name

Month Day, Year

What this page is doingThe title stresses that risk planning sets the rules for later risk decisions before any specific risk is analyzed.
2

Deciding How to Decide: A Risk Management Plan for a Packaging Line Installation

The Project

A pharmaceutical client has contracted us to package a new tablet in blister packs beginning next fall. We will buy a thermoforming blister line from a German manufacturer, install it in a cleanroom suite, connect it to our serialization system and validate it under current good manufacturing practice before the client's first batch. The project has a budget of $2.4 million, a fixed client start date and a validation requirement that cannot be shortened.

Why Plan First

Kendrick (2015) argues that project risk management begins with planning the project well, because many risks only become visible once the work is broken down and scheduled, and that the risk process itself must be agreed early so the team treats risks consistently. Guidance from the Project Management Institute (2019) describes a risk management plan as the document that sets how risk activities will be structured and performed, including methodology, roles, funding, timing, categories and definitions of probability and impact.

Roles

RoleResponsibility
Project managerRuns the risk process, maintains the register, reports to sponsor
Risk ownersNamed for each risk; plan and carry out responses
Validation leadOwns regulatory and qualification risks
Sponsor, operations directorApproves use of contingency reserve; decides on risks above threshold
Client quality representativeReviewed on risks affecting validation or start date

Risk Categories

Six categories guide identification: technical (equipment and integration), vendor (fabrication and delivery), regulatory and validation, resources (people and skills), facility (cleanroom and utilities) and client (requirements and approvals).

Probability and Impact Scales

A risk's score is probability times the higher of its schedule or cost impact rating. Defining the scales in numbers, rather than words like "likely," reduces the disagreement that comes from people reading the same word differently.

RatingProbabilitySchedule impactCost impact
1 Very lowUnder 10 percentUnder 1 weekUnder $10,000
2 Low10 to 30 percent1 to 2 weeks$10,000 to $40,000
3 Medium30 to 50 percent2 to 4 weeks$40,000 to $100,000
4 High50 to 70 percent4 to 8 weeks$100,000 to $200,000
5 Very highOver 70 percentOver 8 weeksOver $200,000

Thresholds and Escalation

Risks scoring 12 or more are reported to the sponsor within two days; risks scoring 15 or more, or any risk threatening the validation date, are reported to the client. Hillson and Murray-Webster (2007) argue that the risk attitudes of individuals and organizations shape how risks are judged, and that stating thresholds explicitly makes those attitudes visible rather than leaving them to chance. Our client is highly averse to start-date risk and moderately tolerant of cost risk, so the thresholds weight schedule more heavily.

What this page is doingSetting thresholds from the client's stated risk attitude, rather than a default number, ties the plan to what actually matters to this project's stakeholders.
3

Reserves

The plan sets a contingency reserve for identified risks, sized by the expected monetary value analysis in Module 4, and a management reserve of 5 percent of budget, $120,000, held by the sponsor for unknown risks.

Reporting and Review

The risk register will be reviewed every two weeks at the project meeting and before each phase gate: design approval, factory acceptance testing in Germany, installation and the start of validation. A one-page risk summary will go to the sponsor every two weeks.

Opportunities

Hillson (2002) argued that the risk process should address opportunities as well as threats. The plan includes them: for example, the chance that the vendor finishes early, which we could use to begin operator training sooner.

Conclusion

The plan sets the rules for every later risk decision: who owns what, how risks are scored, when they are escalated, how reserves are used and how often the register is reviewed. Agreeing these rules now prevents arguments about them later, when a real risk arrives.

References

Hillson, D. (2002). Extending the risk process to manage opportunities. International Journal of Project Management, 20(3), 235-240. https://doi.org/10.1016/S0263-7863(01)00074-6

Hillson, D., & Murray-Webster, R. (2007). Understanding and managing risk attitude (2nd ed.). Gower.

Kendrick, T. (2015). Identifying and managing project risk: Essential tools for failure-proofing your project (3rd ed.). AMACOM.

Project Management Institute. (2019). The standard for risk management in portfolios, programs, and projects. Project Management Institute.

PJM 5300 Module 1 instructions, in plain terms

PJM-5300 grades five discussions, four written assignments, three exercises, four case studies and a final project of 15 to 20 pages that applies a range of risk management principles to a project. The text is Kendrick's Identifying and Managing Project Risk. This first written assignment covers risk planning. Expect to prepare a risk management plan for a project, setting roles, categories, rating scales, thresholds, reserves and a review cycle, and to explain why each choice fits the project. Pick a project you can follow all term, because each later assignment builds on this plan. Define probability and impact in numbers, name who decides when a threshold is crossed and explain how the plan fits the stakeholders' tolerance for schedule and cost risk.

How the PJM 5300 Module 1 example is put together

The paper describes the project and explains why risk planning comes first, with the textbook and a professional standard. Tables set out roles and probability and impact scales, and a section lists six risk categories. Sections define thresholds linked to the client's risk attitude, reserves for known and unknown risks, a review cycle tied to phase gates and the place of opportunities. The conclusion states the plan's purpose. Thresholds are set from the client's stated aversion to schedule risk, and reviews are tied to the project's phase gates, from design approval to the start of validation, so the plan follows the project's real rhythm. A section on opportunities shows the plan covers upside as well as threats.

Where the marks sit in the PJM 5300 Module 1 rubric

Written assignments earn marks for accurate use of risk management concepts, a plan specific to the project, clear reasoning and organized writing. Plans with numeric scales and explicit thresholds show rigor. Linking thresholds to stakeholders' risk attitudes demonstrates understanding beyond templates. Including opportunities and separating contingency from management reserve shows command of the full risk process. Tying review timing to phase gates and thresholds to the client's risk attitude shows that the plan was built for this project rather than copied. Defining both kinds of reserve and who controls each shows financial discipline. Plain tables for roles and scales let the team use the plan without rereading it.

PJM 5300 Module 1 help from the desk

Students lose points by copying a generic template, by defining probability with vague words or by leaving out who decides on escalations and reserves. Others treat risk only as threats. Make every element specific to your project. Define scales with numbers. State thresholds and who acts on them. Include opportunities and both kinds of reserve. Tie reviews to your project's phase gates, and set thresholds from what your client or sponsor can actually tolerate. Write the plan so a new team member could follow it on day one. A free first sample on your own PJM-5300 risk planning assignment is available on request.

Write yours, or have the desk draft it

This paper is an original model document written by our desk, not a submitted student paper and not an official Thomas Edison State University document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.

More PJM 5300 and M.S. in Management in Project Management sample papers

PJM 5300 Module 1 questions, answered

Where can I find a free PJM 5300 Module 1 sample paper?

A risk management plan for a blister packaging line installation is the assignment above.

What does a risk management plan include?

Methodology, roles, categories, probability and impact definitions, thresholds, reserves and the timing of reviews.

Why define probability with numbers?

Words like likely mean different things to different people, so numeric ranges reduce disagreement.

What is the difference between contingency and management reserve?

Contingency reserve covers identified risks; management reserve covers unknown risks and is held by the sponsor.

What textbook does PJM-5300 use?

Kendrick's Identifying and Managing Project Risk, third edition, from AMACOM.