MAN 4350 Module 6 Control and Closeout Written Assignment Example

Reviewed by Edgar Pennington, MBA Thomas Edison State University Updated October 2026

This MAN 4350 Module 6 sample is the last written assignment for Project Management, controlling and closing a composite Hammonton blueberry cooperative's optical sorting line. Prepared for TESU's B.S. in General Management, it reports earned value at week 10, with schedule and cost indexes both at 0.94, and explains why the earlier crashing decision left a late cooling room nearly critical. Two forecasts at completion are compared, a weekend crew and a contingency drawdown correct the slippage, and the closeout traces acceptance on May 15, the handover, the end of the project by integration and three lessons with owners, judged against ten critical success factors. Search the catalog for MAN-4350 to find the course.

CourseMAN-4350 Project Management
ModuleModule 6
Paper typeWritten assignment 6: project evaluation and control; closeout and termination
LengthAbout 1,035 words, 6 pages
FormatAPA 7 student paper
SchoolThomas Edison State University
ProgramB.S. in General Management
UpdatedOctober 2026

Free sample paper for MAN 4350 Module 6

1

Behind by $75,000 of Work at Week Ten, Accepted on May 15: Controlling and Closing a Blueberry Cooperative's Sorting Line

Student Name

B.S. in General Management, Thomas Edison State University

MAN-4350: Project Management

Mentor Name

Month Day, Year

What this page is doingThe title pairs the control finding with the closeout date so the reader sees both halves of the module. The cooperative is a composite.
2

Behind by $75,000 of Work at Week Ten, Accepted on May 15: Controlling and Closing a Blueberry Cooperative's Sorting Line

This final written assignment follows the composite Hammonton cooperative from earlier modules, Mullica Valley Growers, and its new optical sorter from a status review in the middle of the work to its closeout after the first harvest. The project began on January 19 with a performance baseline of $2,227,000, which includes the $24,000 paid to the vendor for an earlier production slot, plus $152,240 of remaining contingency held outside the baseline. The first part evaluates the project at the end of week 10 using earned value; the second describes how the project was closed and what it taught the cooperative. I led the work as the cooperative's operations coordinator, managing the project alongside my regular job.

Earned Value on March 30

Pinto (2019) argues that tracking spending against the budget alone can mislead, because it says nothing about how much work has been done for the money. Earned value management combines scope, schedule and cost in three figures: planned value (PV), what the work scheduled by the status date was budgeted to cost; earned value (EV), the budget for the work actually finished; and actual cost (AC), what was spent. Anbari (2003) shows how these support simple indexes and forecasts that a manager can act on.

At the end of the tenth week of work, on March 30, the figures were as follows.

MeasureValue
Budget at completion (BAC)$2,227,000
Planned value (PV)$1,265,000
Earned value (EV)$1,190,000
Actual cost (AC)$1,262,000
Schedule variance (EV minus PV)minus $75,000
Cost variance (EV minus AC)minus $72,000
Schedule performance index (EV / PV)0.94
Cost performance index (EV / AC)0.94
Estimate at completion (BAC / CPI)about $2,362,000

What the Figures Mean

The project had completed $75,000 less work than planned and had spent $72,000 beyond what the finished work was budgeted to cost. Both indexes stood at 0.94. Almost all of the problem sat in two places. The cooling room contractor was a week and a half behind because insulated panels arrived late, and the panels themselves had cost $58,000 more than quoted after a price increase. The rest of the cost variance came from the abandoned drain line found under the sorter foundation.

The schedule finding mattered more than its size suggested. Crashing the equipment slot had moved acceptance to May 11 but had cut the cooling room's float from three weeks to one. A week and a half of delay therefore threatened to push the finish past May 11 even though the equipment was on time. This is the kind of hidden interaction that makes control more than a matter of reading numbers.

If the cost overrun continued at the same rate, the estimate at completion would be about $2,362,000, roughly $135,000 over the baseline and within the remaining contingency of $152,240, but with little left. If the overrun was a one-time event, the estimate would be actual cost plus the remaining budgeted work, about $2,299,000. Because the panel price was a single event, the second figure was the more realistic forecast, but I reported both to the general manager.

What this page is doingGiving two forecasts and explaining which is more credible shows the mentor that earned value is being interpreted, not only calculated.
3

Corrective Action

Two actions were agreed. First, the refrigeration contractor added a Saturday crew for four weeks at a cost of $9,600, recovering the lost week and a half and restoring the cooling room's float. Second, the contingency was formally drawn down for the panel increase and the drain line, and the remaining contingency was reported to the board, so that no further spending decisions would be made on the assumption that money was still available. By week 14 the SPI had risen to 0.99.

Closeout and Termination

The line passed its acceptance test on May 13, 14 and 15, packing an average of 126,000 pounds a day with 1.6 percent soft or damaged fruit in the sampled clamshells. The first berries arrived on May 29. Final cost was $2,341,000, within the authorized total.

Pinto (2019) describes termination as a set of tasks rather than a single event: finishing the work, handing the project over, gaining acceptance, harvesting the benefits, reviewing how it went, completing the records and disbanding the team. Handover took the form of a signed acceptance by the general manager and the line lead, and a binder of maintenance procedures for the shop. The benefits were tracked through the first season against the selection estimate. Records, including the vendor warranty, final invoices and the risk and issue logs, were filed with the bookkeeper. The team held a closing lunch, and I wrote a short note to each member's supervisor describing the member's contribution.

The textbook also distinguishes ways projects end. This one ended by integration: the new line and its people were absorbed into the packing house's normal operations, and the project organization dissolved.

Evaluation and Lessons

Pinto and Slevin (1987) identified ten factors linked to successful implementation, including top management support, client consultation, monitoring and feedback, and troubleshooting. Looking back, the project was strongest on support and client consultation: the board's backing was clear, and the line leads helped choose the grading settings. It was weakest on monitoring early in the work, since the cooling room delay was found at the week-10 review rather than when the panel order slipped.

Williams (2008) found that organizations often collect lessons from projects but rarely use them. To avoid that, the post-project review recorded three lessons, each with an owner. Order long-lead materials for every contractor, not only the main vendor, before signing. Check float on every path after crashing, not only the path being crashed. And report earned value every two weeks rather than monthly. The general manager added these to the checklist for the freezing tunnel project planned for next year.

Conclusion

Earned value showed at week 10 that the project was slightly behind and over cost, and, more usefully, that the earlier crashing decision had made the cooling room nearly critical. A weekend crew and a formal contingency drawdown corrected both problems. The project closed on time and within its authorized total, ended by integration into operations, and left three specific lessons attached to the cooperative's next project.

References

Anbari, F. T. (2003). Earned value project management method and extensions. Project Management Journal, 34(4), 12-23. https://doi.org/10.1177/875697280303400403

Pinto, J. K. (2019). Project management: Achieving competitive advantage (5th ed.). Pearson.

Pinto, J. K., & Slevin, D. P. (1987). Critical factors in successful project implementation. IEEE Transactions on Engineering Management, EM-34(1), 22-27. https://doi.org/10.1109/TEM.1987.6498856

Williams, T. (2008). How do organizations learn lessons from projects: And do they? IEEE Transactions on Engineering Management, 55(2), 248-266. https://doi.org/10.1109/TEM.2007.912920

Reading the MAN 4350 Module 6 assignment instructions

The sixth module of MAN-4350 covers project evaluation and control and also closeout and termination, the widest set of objectives in the course: leadership attributes, scope management, designing solutions to prevent project failure, the purpose and processes of termination, and project management tools. The written assignment draws on Pinto's final chapters. Expect to calculate or interpret earned value measures, recommend action from them and explain how projects are closed, including the types of termination and the post-project review. Continuing the project you used in earlier modules makes the evaluation far more convincing. Pick a status date partway through the work, so that the numbers have something to say about the rest of the project.

Inside the MAN 4350 Module 6 example

The paper states the baseline, contingency and status date before any calculation. A table reports PV, EV, AC, both variances, both indexes and an estimate at completion. The interpretation traces the variances to their causes and links the cooling room delay to the earlier crashing decision. Two forecasts are compared and the more credible one explained. Corrective action names costs and results. The closeout section works through the textbook's termination tasks and type of ending, and the evaluation uses critical success factors and research on lessons learned to produce three lessons with owners. The paper closes the story begun in Module 1, so the six assignments tell a single story, from selection to handover.

Reading the MAN 4350 Module 6 grading rubric

This final MAN-4350 written assignment earns a score between 0 and 100 and shares the 30 percent written-assignment weight with the other five. Mentors look for correct earned value calculations, an interpretation that explains causes and consequences, and corrective actions that follow from the analysis. The closeout portion should show an understanding of termination as a process, with handover, acceptance, records, benefits and team release, and a review that produces usable lessons. Support from research, clear tables and accurate APA style strengthen the paper. Linking control findings to earlier planning choices shows the integrated view this last module is meant to test, since control problems often begin with decisions made months earlier.

Common MAN 4350 Module 6 mistakes, and how to avoid them

Students often calculate SPI and CPI correctly and then stop, without saying what caused the variances or what to do about them. Another common mistake is using a single estimate at completion without asking whether the overrun will continue. Closeout sections are frequently one paragraph about a party; the textbook expects handover, acceptance, records and lessons. Make each lesson specific and give it an owner, then say where the lesson will be used next. A lesson without an owner and a next project is only an observation. Our writers can prepare a MAN 4350 control and closeout assignment using the project you have followed through the course.

Write yours, or have the desk draft it

This paper is an original model document written by our desk, not a submitted student paper and not an official Thomas Edison State University document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.

More MAN 4350 and B.S. in General Management sample papers

MAN 4350 Module 6 questions, answered

Where can I find a free MAN 4350 Module 6 sample paper?

The final Project Management written assignment is reproduced in full above: an earned value status report, corrective action, and the closeout and lessons of a cooperative's sorting-line project, with references.

What do SPI and CPI tell a project manager?

The schedule performance index (EV divided by PV) shows the rate of work done against plan, and the cost performance index (EV divided by AC) shows the value of work done per dollar spent; values below 1.0 signal trouble.

How do you forecast the estimate at completion?

Divide the budget at completion by the CPI if the overrun is expected to continue, or add the remaining budgeted work to actual cost if it was a one-time event.

What are the ways a project can be terminated?

Common types include termination by extinction, by addition, by integration into the parent organization and by starvation of resources.

Which course objectives does MAN-4350 Module 6 cover?

Leadership attributes, scope management, designing solutions to prevent failure, project termination and project management tools and techniques.